Paris North Boundary Review
On September 28, 2026, the Grand Erie District School Board of Trustees approved the commencement of the Boundary Review.
The Review involves:
- Paris Central Public School
- North Ward School
- Cobblestone Elementary School
- Burford District Elementary School
- Glen Morris Central Public School
As the Paris community in Brant County continues to grow, the need for a new elementary school within the area was necessary. In January 2025, Grand Erie received Ministry of Education approval and funding for a new 536-pupil-place elementary school and 64-space childcare facility, located south of Watts Pond Road and east of Pinehurst Road. The school is anticipated to open in September 2028.
The Paris North Boundary Review will establish a boundary for the new school and will likely impact families who currently live, or will live, in the surrounding area.
Meeting Dates
Meeting format: You can expect a brief presentation and an opportunity for your questions and feedback.
If you are unable to attend but would still like to contribute, you may submit your questions to planning@granderie.ca
- Wednesday, Oct. 28 from 6 to 7:30 p.m.
Map
The following map shows the Proposed Attendance Boundaries for Paris Elementary Schools
Capacity Impacts
Table 1: Existing and projected enrolment: initial accomodation option
| Enrolment1 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Prior to New School Opening | After New School Opening | |||||||||||
| School | Capacity | Current Portables | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | 2031 | 2033 | 2035 | 2037 |
| Burford District Elementary School | 541 | 2 | 505 | 508 | 503 | 506 | 514 | 520 | 520 | 520 | 535 | 544 |
| Cobblestone Elementary School2 | 720 | 4 | 595 | 596 | 600 | 601 | 472 | 481 | 508 | 549 | 572 | 620 |
| Glen Morris Central Public School | 176 | 0 | 204 | 213 | 207 | 201 | 195 | 196 | 210 | 224 | 235 | 258 |
| North Ward Public School | 489 | 0 | 504 | 521 | 514 | 503 | 438 | 449 | 452 | 446 | 450 | 468 |
| Paris Central Public School | 259 | 0 | 243 | 257 | 269 | 275 | 181 | 182 | 188 | 192 | 201 | 211 |
| New Paris School | 236 | 0 | 0 | 0 | 0 | 0 | 374 | 391 | 421 | 445 | 457 | 486 |
| Total | 2721 | 6 | 2051 | 2095 | 2093 | 2086 | 2174 | 2219 | 2299 | 2376 | 2450 | 2587 |
Notes:
1 Including OOB students
2 Cobblestone ES capacity was 536 prior to 2026
Table 2: Existing and projected utilization: initial accommodation option
| Capacity Utilization1 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Prior to New School Opening | After New School Opening | |||||||||||
| School | Capacity | Current Portables | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | 2031 | 2033 | 2035 | 2037 |
| Burford District Elementary School | 541 | 2 | 93% | 94% | 93% | 94% | 95% | 96% | 96% | 96% | 99% | 101% |
| Cobblestone Elementary School2 | 720 | 4 | 111% | 111% | 83% | 83% | 66% | 67% | 71% | 76% | 79% | 86% |
| Glen Morris Central Public School | 176 | 0 | 116% | 121% | 118% | 114% | 111% | 111% | 119% | 127% | 134% | 147% |
| North Ward Public School | 489 | 0 | 103% | 107% | 105% | 103% | 90% | 92% | 92% | 91% | 92% | 96% |
| Paris Central Public School | 259 | 0 | 94% | 99% | 104% | 106% | 70% | 70% | 73% | 74% | 78% | 81% |
| New Paris School | 236 | 0% | 0% | 0% | 0% | 0% | 70% | 73% | 79% | 83% | 85% | 91% |
| Total | 2721 | 6 | 75% | 77% | 77% | 77% | 80% | 82% | 84% | 87% | 90% | 95% |
Notes:
1 Including OOB students
2 Cobblestone ES capacity was 536 prior to 2026